An update on transportation projects in Albemarle County

(This segment originally appeared in the May 29, 2021 edition of Charlottesville Community Engagement)

At the height of the Great Recession earlier this century, Albemarle County froze many positions and slowed contributions to its capital improvement program. One job that was not filled for many years was transportation planning, but for the past few years, Albemarle has put together an organized list of potential projects to address road capacity issues as well as bike and pedestrian connections.

In July 2019, they adopted a priority list ranging from Hydraulic/29 Improvements at #1 to U.S. 250 West / Gillums Ridge Road Intersection Improvements at #89. 

“That list provided all capital transportation projects that are recommended through the various county planning processes,” said Kevin McDermott , a chief of planning in Albemarle, in a May 19 to the Board of Supervisors. (review the update)

The list is intended to help planners identify funding sources for projects, such as the Virginia Department of Transportation’s Smart Scale program as well as the county’s own capital improvement program.  

“We have gotten 12 projects from that 2019 project list funded,” McDermott said. 

  • Hydraulic 29 / Improvements, including a pedestrian bridge over U.S. 29 and a roundabout at Hillsdale and Hydraulic, are slated to be funded at $24 million by Commonwealth Transportation Board in June (#1)
  • U.S. Route 250 improvements to add median between Route 20 and Rolkin Road to receive $6 million in Smart Scale funding using $2 million in local funds (#2)
  • Route 20 / U.S. 250 intersection will be rebuilt using funding from 2018 Smart Scale round sometime in 2024 (#3)
  • Berkmar Drive will be extended further north to Lewis and Clark Drive, providing a continuous roadway to UVA North Fork Research Park. Funding came from VDOT’s revenue sharing program.
  • Further changes to Fontaine Avenue / U.S. 29 intersection including a shared-use path (#6)
  • A roundabout will be built at Old Lynchburg Road and 5th Street Extended with $5 million in VDOT funds and $2 million in Albemarle funds (#7)
  • A roundabout at Rio Road and the John Warner Parkway is recommended for $8 million funding in the current Smart Scale process and $2 million in Albemarle funds will be used (#15)
  • Bike and pedestrian improvements will be made on Old Lynchburg Road using Albemarle funds (#26)
  • A section of the Northtown Trail shared-use path will be built between Seminole Lane North and Carrsbrook Drive at a cost of $4 million (#35)
  • A greenway trail on Moores Creek and a trail hub at 5th Street Station will receive Smart Scale funds and has a total cost of $10 million (#40)
  • A park and ride lot will be constructed near Exit 107 and Crozet Park to serve Jaunt and the future Afton Express at a cost of $3 million (#82)This map depicts location of projects that have received funding since 2019 (Credit: Albemarle County)

McDermott’s purpose for appearing before the supervisors was to get their preliminary support for the next round of transportation projects. At the top of a short list for this year’s cycle of VDOT revenue-sharing funds is the completion Eastern Avenue, a north-south roadway designed to increase connectivity and traffic circulation throughout Crozet. 

“That project is currently being evaluated through an alignment study and conceptual design which the county has funded through our transportation leveraging project,” McDermott said. “We have just recently received the updated cost estimates from that consultant we have hired and their preliminary cost estimates are now at $19,983,000.” 

That would require at least a $10 million match from county funds. However, if approved the state funding would not be available until 2027. 

Another project on the list for potential revenue-sharing projects is one to build bike and pedestrian improvements on Mill Creek Drive to Peregory Lane, a top priority in a recent corridor study. That has a cost estimate of $2 million. 

Applications  for revenue-sharing projects are due this year.  Next year Smart Scale projects will be due. Potential applications to be made next year include a roundabout at District Avenue and Hydraulic Road, a realignment of Hillsdale Drive, and a roundabout at the intersection of Belvedere Boulevard and Rio Road. 

There’s plenty of time to get involved with these applications. Keep reading and stay tuned.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.