The focal point of planning in Albemarle County is currently the area between Airport Road and Ashwood Boulevard, a key intersection on what the Virginia Department of Transportation considers a “corridor of statewide significance.”
In August, the Board of Supervisors ratified a decision by staff in the Department of Community Development to select that area as the first to receive planning attention through the new “Activity Center Plan.”
VDOT is conducting what is known as a Project Pipeline study at the intersection of U.S. 29 and Route 649, which is known as Airport Road to the west and Proffit Road to the east.
“The purpose of the study is to address safety, capacity and multimodal needs at the intersection,” reads an information release that went out on November 10. The survey is open through November 24 and can be taken here.
“Community input received through these surveys will help the study teams identify existing issues within the study intersectations (sic) and develop recommendations for potential improvements that will be evaluated and presented during the next phase of the studies, which will include another opportunity for public comment,” the release continues.
VDOT began these “Project Pipeline” studies in 2021 as a way of coming up with ideas for future reconfigurations and infrastructure changes.

Before you go: The goal of Town Crier Productions is to increase awareness about what is happening at the local, regional, state, and federal government levels. Please share the work with others if you want people to know things.
Paid subscribers cover the cost of conducting research for this article which was originally published in the November 23, 2026 edition of Charlottesville Community Engagement. You can either subscribe through Substack or make a charitable contribution.
Discover more from Information Charlottesville
Subscribe to get the latest posts sent to your email.